S-Curve Kemajuan
Bandingan perancangan vs sebenar sepanjang tempoh projek
Milestone & Fasa
Inisiasi
Mar 24 → Apr 24
100%
Selesai
Perancangan Keperluan
Apr 24 → Jul 24
100%
Selesai
Rekabentuk Sistem
Jun 24 → Sep 24
92%
Aktif
Pembangunan Fasa 1
Aug 24 → Dec 24
68%
Aktif
Pembangunan Fasa 2
Nov 24 → Mar 25
24%
Aktif
SIT / UAT
Feb 25 → May 25
0%
Akan Datang
Cutover & Go-Live
May 25 → Jun 25
0%
Akan Datang